Client brief:
To construct a gantry to house media staff and new TV cameras following promotion to the Premier League.

Scaffold requirements:

  • Working closely with designers, works were completed to meet tight client deadlines, to give safe access to install additional camera booths
  • The build to install the camera booths required a 5 lift x 111 metre x 8 metre birdcage scaffold covering the length of the Jarrold stand
  • A 9 lift x 6 metre x 4 metre scaffold was required around the existing stairwell to install access to the new camera booths
  • A Haki staircase system was erected to allow safe access to the working platform
  • Please see video on website for further details
  • Scaffold was inspected and Scaff Tagged upon completion by the Site Supervisor
  • Weekly inspections were carried out throughout the project by one of our Advanced Scaffold Inspectors
Tubes Scaffolding
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.